Huron Center

Project Completed - December 2018

20180823_weinrauch_northglenn-huron-project_0001
The  $13 Million revitalization of the Huron Center was completed in December 2018.

The  Huron Center has been revitalized and redeveloped.


In partnership with the two property owners  and the Northglenn Urban Renewal Authority (NURA), the shopping center has been revitalized and more than $3.2 million of above and underground infrastructure has been installed.

Goals
  • Revitalize the aged center into a thriving shopping center for residents and visitors.
  • Retain and attract quality tenants to the center.
  • Improve utility infrastructure for the center and surrounding area.
  • Re-energize and improve the appearance of the center.

Features

 
Location
1000 W. 104th Ave., Northglenn


Funding
The exterior improvements and infrastructure cost approximately $11 million. NURA funded about $3.2 million, while the two property owners provided the rest.

Timeline

  • January 9, 2019 
    Save-A-Lot held its grand opening.
  • August 2018
    New facades installed and construction complete. 

  • June 26, 2018
    AutoZone held its grand opening.

  • June 21, 2018
    Arby's held its grand opening.

  • March 2018

    When the 'now hiring' signs are posted, you know business construction is progressing. At the Huron Center on 104th Avenue, pedestrians and motorists can view signage for the future AutoZone and Arby's, as well as signs seeking employees. Those two businesses, along with Save-A-Lot supermarket, should all be open by early fall.

  • Feb. 2, 2018
    Save-A-Lot announces they will be coming to the Huron Center.

  • November 2017

    The new configuration for the north parking lot at the Huron Center has been established.

  • Oct. 30, 2017
    Crews are working hard on the renovation of the Huron Center. Here is a schedule update:
    • Façade: Slated for completion in mid to late November with finishes.
    • North side parking lot: Groundwork and grading are scheduled to be done the first week of November, with asphalt and paving set for completion by mid-November.
    • South and east side parking Lot: Work will immediately follow completion of the north parking lot. Ground preparation and asphalt placement is expected to be done by mid to late December for the east lot and in early to mid-January on the south side.
      Please note that these are estimates, and could change based on a number of factors, including weather.

  • Aug. 24, 2017
    Huron_Center_Groundbreaking_dirt_toss_DSC_1156_ngcrop_web
    The mayor and City Council members, along with members of the Northglenn Urban Renewal Authority and Huron Center property owners attended the official groundbreaking ceremony for the revitalization project at the Huron Center.

  • July 31, 2017
    AutoZone announces one of its Mega Hubs will be coming to the Huron Center.

  • July 7, 2017
    Evergreen Development purchased the vacant former Albertson’s/Rite Aid building at 104th Avenue and Huron Street from the Northglenn Urban Renewal Authority (NURA).
     
  • April 3, 2017
    The Northglenn Urban Renewal Authority (NURA) approved agreements with Evergreen-104th & Huron, L.L.C., and Impala Capital, LLC, to redevelop the 10.45-acre, 104,322-square-foot Huron Center. Impala owns the multi-tenant shops buildings east and west of the Evergreen property plus two outlet restaurant buildings.

  • May 2014
    NURA purchased the 57,442 square-foot former Albertson’s/Rite Aid property in May 2014 to position it for redevelopment.


Documents


Related Information
Contact

Debbie Tuttle
Economic Development Manager
303.450.8743
dtuttle@northglenn.org

City Hall
11701 Community Center Drive
Northglenn, CO 80233

twitterfacebook