This 45,000-square-foot facility will be the future home of the Police Department and Municipal Court.

Over the years, the current space has become too small. Built in the early 1980s, the building is beginning to show significant signs of age. The aging mechanical systems, and the size and configuration of the space simply don’t meet the needs of the department, or modern police department standards.

Location

On a six-acre site at the intersection of Community Center Drive and West 112th Avenue, overlooking Interstate 25.

Funding

The cost of the building is $18M; additional ancillary costs put the total in the $21-$23M range.

Timeline

  • 2014 - An assessment identified spatial and functional needs and the plan for a new building started to move forward
  • April 2017 - Construction began
  • Fall 2018 - Scheduled opening. You can take tours once the facility is complete.

Updates

Jan. 9
The contractor on the Justice Center is continuing to work on mechanical, electrical and plumbing installation on the interior of the building. Exterior work includes insulation, masonry, and glass installation. The contractor will begin drilling foundations for the new traffic signal in the upcoming weeks. Also, portions of the north parking lot have been constructed. Click here for photos.
***

Dec. 27
Construction crews focus on the outside of the Northglenn Justice Center while the weather is still relatively warm and dry. That way, when winter sets in, they can move inside and continue work.
***
Mid November
With winter set to pounce on the Front Range at any time, the contractor for the Northglenn Justice Center is focused on finishing the exterior before the cold weather settles in. On the inside, the priority is the masonry.
***
Oct. 30
The contractor has begun limited backfilling around the building and expects to complete the north foundation wall shortly. Masonry work has begun on the interior and will be a focus of the contractor coming up. The contractor's main goal is to complete the exterior of the building, protecting the interior from winter conditions.
***
Oct. 4
The contractor will begin working on grading the detention pond and channels. Backfilling of the foundation wall is ongoing. Domestic water and water meter box installs are underway this week. Interior masonry priority walls are underway.
***
Sept. 22
The contractor will be completing structural steel this week. The first concrete pour on the deck has been completed with the second pour (East Main Deck and Rotunda) scheduled for Friday. Interior masonry priority walls are underway and will continue for some time. Backfilling of the foundation began this week and will continue for two to three weeks.
***
Aug. 16
The contractor is setting the structural steel for the building. When this is completed crews will begin placing concrete for the upper floors.
***
June 29: Lower Level Floors and Walls Taking Shape
The concrete foundation walls and grade breams have been formed. The first of three concrete slabs that will form the floor of the building has been poured. Utility, sanitary and sewer work continues.
***
June 8
Concrete placement for the east and west grade beams is complete. Concrete is placed for the east and center foundation walls, and work continues on forming the remaining walls and grade beam. The construction manager has begun installing the under-slab plumbing and electrical. Upcoming work includes: continuing construction of the walls, the grade beam, and plumbing and electrical. The first of three slab pours is scheduled tentatively for 6/23.
***
May 18
The site has been graded to allow work on the foundation to begin. They have installed 129 watertight retaining structures and will be forming and reinforcing walls in the next few weeks. Utility work on the sanitary line at Acoma Street is underway and should be completed in three weeks.

Photos

embedded photo section

>Frequently Asked Questions

Related Information

Contact

Someone
303.450.8992
police@northglenn.org

City of Northglenn
11701 Community Center Drive
Northglenn, CO 80233
303-451-8326