Huron Center Redevelopment

Artist rendition of Huron Center

Huron Center Redevelopment

Redevelopment of the Huron Center at 1000 W. 104th Ave is underway.

On July 7, 2017, the Evergreen Development purchased the vacant former Albertson’s/Rite Aid building at 104th Avenue and Huron Street from the Northglenn Urban Renewal Authority (NURA).

NURA purchased the 57,442 square-foot former Albertson’s/Rite Aid property in May 2014 to position it for redevelopment.

On April 3, 2017, the Northglenn Urban Renewal Authority (NURA) approved agreements with Evergreen-104th & Huron, L.L.C., and Impala Capital, LLC, to redevelop the 10.45-acre, 104,322-square-foot Huron Center. Impala owns the multi-tenant shops buildings east and west of the Evergreen property plus two outlot restaurant buildings.

New businesses that will move into the shopping area, located at 104th Avenue and Huron Street, include:
A 35,669-square-foot AutoZone Mega Hub
• A 21,773-square-foot neighborhood grocer
A newly-constructed, 2,400-square-foot Arby’s restaurant

Project construction has begun and is scheduled to be complete on the majority of the project by the first quarter of 2018, and the new tenants plan to open in the summer of 2018.

Updates

Oct. 30, 2017
Crews are working hard on the renovation of the Huron Center. Here is a schedule update:
• Façade: Slated for completion in mid to late November with finishes.
• North side parking lot: Groundwork and grading are scheduled to be done the first week of November, with asphalt and paving set for completion by mid-November.
• South and east side parking Lot: Work will immediately follow completion of the north parking lot. Ground preparation and asphalt placement is expected to be done by mid to late December for the east lot and in early to mid-January on the south side.
Please note that these are estimates, and could change based on a number of factors, including weather.
***
Aug. 24, 2017

The City of Northglenn Mayor and City Council members, along with members of the Northglenn Urban Renewal Authority and Huron Center property owners attended the official groundbreaking ceremony for the revitalization project at the Huron Center.

City of Northglenn
11701 Community Center Drive
Northglenn, CO 80233
303-451-8326