Glenn Park PlayGround
Officers and volunteers from the Northglenn Police Department installed playground equipment at Glen Park Village Apartment in an effort to make a safe and enjoyable atmosphere for children in our community.
|
|
|
| capital improvement projects |
120th Avenue & Grant Street Improvement Project
Updated by Project Manager: Joliette Woodson
This capital improvement project is a major cooperative project between the cities of Northglenn and Thornton. The improvements include double left turn lanes on all intersection legs, storm drainage, landscaping, utilities, pedestrian trail, and traffic signal improvements. Construction is scheduled to be complete August 13, 2007. | | Washington Fence Project
Updated by Project Manager: Nicholas DiFrank
The final chapter of the Washington Street fence project is currently under construction and runs from Phillips Drive to Sylvia Drive. The project includes the traditional 6ft Northglenn Brick Pilasters and Cedar Picket Fencing. Construction is scheduled to be complete by July 15, 2007. | | Water Treatment Plant Clearwell/Administration Addition
Updated by Project Manager: Amy Ward
The design of the Water Treatment Plant Clearwell Addition has been completed by The Engineering Company (TEC) out of Fort Collins. This addition to the clearwell is required to meet new regulatory requirements from the Colorado Department of Public Health and Environment (CDPHE). The project is currently under review with the for the construction approval of a modification to the treatment system. The City anticipates receiving official confirmation for the construction of the clearwell addition from the CDPHE at the beginning of July. This project has been reviewed by the Development Review Committee and the Planning Commission and will go out for bid once comments are addressed. The project is anticipated to bid at the end of July and the construction will take approximately a year to construct.
The Water Treatment Plant Administration Building project went out to bid earlier this year and Construction Concepts, Inc. was the contracting company selected to construct the building. The building will replace the trailer that was burnt in a fire last year and will house the water operations and E&M staff. The building was designed by The Engineering Company and is equipped with six offices, five cubicles, a kitchen, copy area, conference room, electrical room, mechanical room and restrooms. The construction is currently underway and is set for completion at the beginning of September. The post-tension slab has been set and the Contractor has begin framing the building.
One of the fume hoods at the Water Treatment Plant is not performing properly and must be replaced. The fume hood is used by the laboratory analysts to testing of the water and wastewater in the City. The City is currently waiting fro quotes from vendors to provide and install the equipment. The project should be complete by early fall of this year. | | Wastewater Treatment Plant Headworks/Security Fencing
Updated by Project Manager: Amy Ward
Carollo Engineers is the consulting firm selected to complete the design of the Wastewater Treatment Plant Headworks. A headworks facility is typically designed to remove trash and grit from the waste stream prior to treating the wastewater and is normally done with the use of screens and grit chambers. Also included in the design, is an evaluation of the functionality of the current plant as well as an evaluation the odor problems at the wastewater treatment plant and at lift station “A”. The design is currently in the preliminary stages and final design is anticipated for completion towards the end of the year.
Due to insurance requirements, the new Wastewater Treatment Plant is required to be fenced to limit the access to the facility. The design of the fence is currently being performed by City staff and is the design is anticipated to be complete by the end of June. |
|
|
|
|
|